Wexner Medical Center Garage

The Ohio State Wexner Medical Center strategic plan calls for growth and expansion as a key element. As a first step toward a new inpatient tower, the Wexner Medical Center Garage will serve patients and visitors and house 1,887 spaces. 

The facility opened in December 2020 to parkers with the full project scheduled to be complete in May 2021. The $102.1 million expansion supports the additional patient rooms in the new tower with up to 820 beds replacing and expanding on the 440 beds in Rhodes and Doan.

Learn more about how Ohio State in investing in the spaces and places that empower collaboration by visiting Ohio State Environments.

Project Timeline

  • 2018
  • 2019
  • 2020
  • 2021

Project Team


Project Managers 
Pat Cuthbert

Project Accountant
Brittney Coleman

Consultants
AE/Design Architect: Henningson, Durham & Richardson (HDR)

Construction Manager
Walsh/Turner (joint venture)

News

Fans are back in Ohio Stadium this fall as the Buckeyes make another run toward the College Football Playoffs.

We all love scarlet and gray, but there’s a sea of orange on campus as Ohio State invests in the future of teaching, learning and research. Major construction projects are changing the way most Buckeyes will navigate campus – so allow extra travel time, be cautious near co

Columbus Business First recently wrote about the university seeking Board of Trustees approval this week for Cannon Drive Phase II.