Main navigation

News

  • Slideshow: Campbell Hall

    Construction on Campbell Hall is nearly 45% complete as crews continue duct work, plumbing, electrical, fire suppression and framing across the building. New and existing reroofing is nearly 75% complete. Site work is underway, which includes a new fire suppression service along with clearing and grubbing. An elevator shaft extension is being installed into a new mechanical penthouse....
  • In the News: The New Face of Our Campus

    The Spring 2025 edition of Ohio State’s Alumni Magazine highlighted 23 buildings on the university’s Columbus campus that were supported in part by Time and Change: The Ohio State Campaign. Capital funds from the campaign helped support the addition of new buildings and modernizing ones that have been used by Buckeyes of the past. Read Full Article ...
  • Slideshow: Waterman – Multispecies Animal Learning Center (MALC)

    Exciting developments are underway at the Waterman Agricultural and Natural Resources Laboratory’s Multispecies Animal Learning Center (MALC). With blueprints transforming into reality, a beam signing was held on May 22. Key stakeholders from the College of Food, Agricultural, and Environmental Sciences (CFAES) gathered to celebrate the construction progress and honor the significance of the...
  • Slideshow: Biomedical and Materials Engineering Complex Phase 2

    Construction on the Biomedical and Materials Engineering Complex (BMEC) Phase 2 is about 60% complete as crews are finished framing level one and are now beginning drywall installation. Significant progress has been made in the basement where concrete has been poured, and framing is starting to go up. “As students leave for the summer, you’ll notice even more progress,” said Shaun Allen, Fac...
  • Slideshow: Inpatient Hospital

    Construction on the Wexner Medical Center Inpatient Hospital is at 95% complete as crews have already turned over floors 11, 12 and 14 to the fit-up team, in addition to floors one through ten. Floors 15 and 16 are currently being turned over followed by 17 and 18. Once floors are turned over to the fit-up team, they’re cleaned and then equipment and furniture are installed. Cabling is being...

News Archive