Main navigation

News

  • Slideshow: Inpatient Hospital

    Work on The Ohio State University Wexner Medical Center inpatient tower is nearing 90% complete as crews have turned over the first floor to fit-up, and are now installing furniture, medical equipment, technology, signage and art. 

  • Cannon Drive at Woody Hayes Drive Opens Nov. 16

    Cannon Drive at Woody Hayes Drive is anticipated to open Saturday, November 16. The reopening of the roadway is a major milestone in the Cannon Drive Relocation – Phase 2 project.

  • Slideshow: Campbell Hall

    The renovation of Campbell Hall is nearing the 10% complete mark as crews continue interior work. They’ve completed removing old concrete floors from the building and are now refilling them and bringing them back up to the proper elevation. Underground plumbing is being installed on the ground floor as the penthouse roof is being removed.

  • Slideshow: Inpatient Hospital

    As crews prepare for lower-level turnover to Fit-up in mid-October, construction on The Ohio State University Wexner Medical Center Inpatient Hospital is 85% complete. Once final inspections are complete on the lower level, ground, and Level 1, the Fit-up crews will install furniture, medical equipment, technology, signage and art. 

  • Slideshow: Biomedical and Materials Engineering Complex Phase 2

    Construction on the Biomedical and Materials Engineering Complex (BMEC) Phase 2 is about 45% complete as crews recently finished installing the final concrete piers. The focus is now on ensuring a strong foundation with footers and a foundation wall. Construction on the north and south connectors from Mars G.

News Archive