Main navigation

News

  • Slideshow: Campbell Hall

    The Campbell Hall Renovation project is nearing 25% completion as crews continue their facelift on the historic building. A variety of specialty crews are in and out of the building each day including electricians, plumbers, carpenters and heating, ventilation and air conditioning professionals, among others.

  • Slideshow: Biomedical and Materials Engineering Complex Phase 2

    Work on the Biomedical and Materials Engineering Complex (BMEC) Phase 2 is passing the halfway point, at nearly 53% complete. Crews are preparing to pour the second interior stairwell and then will be able to remove the exterior temporary set. Crews are also working on installing mechanical, electrical and plumbing (MEP) hangers throughout the building.

    Construction progress includes:

  • Slideshow: Waterman – Multispecies Animal Learning Center (MALC)

    The CFAES Waterman Agricultural and Natural Resources Laboratory’s Multispecies Animal Learning Center (MALC) facility is coming to life as crews have begun installation of electrical conduits in the mezzanine area as well as plumbing for restrooms.

  • Slideshow: Outpatient Care Powell

    Work on The Ohio State University Wexner Medical Center Outpatient Care Powell is nearing 33% completion. Crews are just beginning framing and overhead ceiling work on the fourth floor, while already complete on floors two and three. Installation of the roof on the Ambulatory Healthcare Center (AHC) is 80% complete.

News Archive