Main navigation

News

  • Slideshow: Biomedical and Materials Engineering Complex Phase 2

    Work on the Biomedical and Materials Engineering Complex (BMEC) Phase 2 is passing the halfway point, at nearly 53% complete. Crews are preparing to pour the second interior stairwell and then will be able to remove the exterior temporary set. Crews are also working on installing mechanical, electrical and plumbing (MEP) hangers throughout the building.

    Construction progress includes:

  • Slideshow: Waterman – Multispecies Animal Learning Center (MALC)

    The CFAES Waterman Agricultural and Natural Resources Laboratory’s Multispecies Animal Learning Center (MALC) facility is coming to life as crews have begun installation of electrical conduits in the mezzanine area as well as plumbing for restrooms.

  • Slideshow: Outpatient Care Powell

    Work on The Ohio State University Wexner Medical Center Outpatient Care Powell is nearing 33% completion. Crews are just beginning framing and overhead ceiling work on the fourth floor, while already complete on floors two and three. Installation of the roof on the Ambulatory Healthcare Center (AHC) is 80% complete.

  • Slideshow: Inpatient Hospital

    Work on The Ohio State University Wexner Medical Center Inpatient Hospital has reached 92% complete. Floors one through four and seven through 10 have been turned over to the fit-up team to install furniture, medical equipment, technology, signage and art. More than 80,000 new items, not including IT and furniture, are set to be installed over the coming months. 

  • Waterman - Multispecies Animal Learning Center Begins to Take Shape

    The Waterman – Multispecies Animal Learning Center (MALC) facility is beginning to take shape as crews have finished pouring the concrete foundations for the main arena and the structural steel has begun to arrive to start going vertical.

News Archive