Main navigation

News

  • Slideshow: Inpatient Hospital

    Construction on the Wexner Medical Center Inpatient Hospital is at 95% complete as crews have already turned over floors 11, 12 and 14 to the fit-up team, in addition to floors one through ten. Floors 15 and 16 are currently being turned over followed by 17 and 18. Once floors are turned over to the fit-up team, they’re cleaned and then equipment and furniture are installed. 

  • Slideshow: Outpatient Care Powell

    Construction on The Ohio State University Wexner Medical Center Outpatient Care Powell is about 42% done with just about every tradesperson conducting work on the building. From masonry and roofing, to framing and mechanical electric and plumbing (MEP), significant progress is being made. Precast on the exterior of the building is now complete as brick and windows are being installed. 

  • Slideshow: Campbell Hall

    The Campbell Hall Renovation project is nearing 25% completion as crews continue their facelift on the historic building. A variety of specialty crews are in and out of the building each day including electricians, plumbers, carpenters and heating, ventilation and air conditioning professionals, among others.

  • Slideshow: Biomedical and Materials Engineering Complex Phase 2

    Work on the Biomedical and Materials Engineering Complex (BMEC) Phase 2 is passing the halfway point, at nearly 53% complete. Crews are preparing to pour the second interior stairwell and then will be able to remove the exterior temporary set. Crews are also working on installing mechanical, electrical and plumbing (MEP) hangers throughout the building.

    Construction progress includes:

News Archive