
Post tensioning cables and rebar are used to reinforce concrete, once installed.
September 8, 2021
Concrete pours and rebar installation continue on the Dodd Parking Garage, which is more than 30% complete. Overnight concrete pours are ongoing and will continue through January 2022. The garage will have six levels and 1,100 parking spaces for Ohio State faculty and staff.
Additional construction activities include:
Built on the former Dodd surface parking lot, the Dodd Parking Garage is located within walking distance of the Wexner Medical Center. The $33.3 million project is expected to open in June 2022.
View the photo slideshow above to track the project’s progress or view live construction feeds.