The Biomedical and Materials Engineering Complex (BMEC) Phase 2 is a $94.3 million project that maximizes collaborative learning and research. It will be the home of first-year engineering courses, makerspace, biomedical and advanced materials R&D, and engaging K-12 STEM programs.
The project included the demolition of Watts Hall and renovates existing MacQuigg Hall. An addition will be constructed that will house research and teaching labs, collaboration spaces, offices and classroom space. BMEC Phase 1, later renamed Mars G. Fontana Laboratories, opened in August 2020 and was a $59.1 million project that renovated the former Koffolt Lab and Fontana Lab to create additional research, classroom and office space. It houses the Departments of Biomedical Engineering and Materials Sciences and Engineering.
Project Timeline
- 2021
- BOT Professional Services ApprovalFebruary 2021DesignMay 2021 - May 20232023
- BOT Construction ApprovalMay 2023ConstructionAugust 2023 - January 20262026
- Facility OpeningMay 2026
Live Updates
Looking northwest toward the Biomedical and Materials Engineering Complex Phase 2 project.Project Team
Project Manager
Shaun AllenConsultants
AE/Design Architect: DLR GroupConstruction Manager
Walsh ConstructionNews
-
Slideshow: Biomedical and Materials Engineering Complex Phase 2
Work on the Biomedical and Materials Engineering Complex (BMEC) Phase 2 is passing the halfway point, at nearly 53% complete. Crews are preparing to pour the second interior stairwell and then will be able to remove the exterior temporary set.
-
Slideshow: Biomedical and Materials Engineering Complex Phase 2
Construction on the Biomedical and Materials Engineering Complex (BMEC) Phase 2 is about 45% complete as crews recently finished installing the final concrete piers. The focus is now on ensuring a strong foundation with footers and a foundation wall.
-
Slideshow: Biomedical and Materials Engineering Complex Phase 2
Work on the Biomedical and Materials Engineering Complex Phase 2 (BMEC) is nearly halfway complete as crews have made substantial progress over the last several months. A buck hoist has been installed and a platform below it is in place to ensure the safety of everyone on site.