The Campbell Hall Renovation is a $61.2 million project that includes state funding and supports the College of Education and Human Ecology’s educational goals and mission.
The project provides updated space that will promote collaborative work and hands-on learning environments. Campbell Hall Renovation will renovate 115,000 square feet of existing offices, research and computer labs, teaching kitchen, department and pool classrooms and collaborative areas. The project scope will also address existing aging infrastructure by replacing building systems, roof and windows. A 9,000 square foot renovation of office and lab space in Evans Lab for faculty to use during the renovation of Campbell Hall was also included in the project scope.
Project Timeline
- 2021
- BOT Professional Services ApprovalMay 2021DesignDecember 2021 - June 20232023
- BOT Construction ApprovalMay 2023ConstructionJuly 2023 - April 20262026
- Facility Opening (Phased)May 2026
Project Team
Project Manager
Todd HenderlyConsultants
AE/Design Architect: Schooley CaldwellConstruction Manager
CK Construction Group
News
-
Slideshow: Campbell Hall
Construction on Campbell Hall is nearly 45% complete as crews continue duct work, plumbing, electrical, fire suppression and framing across the building. New and existing reroofing is nearly 75% complete. -
In the News: The New Face of Our Campus
The Spring 2025 edition of Ohio State’s Alumni Magazine highlighted 23 buildings on the university’s Columbus campus -
Slideshow: Campbell Hall
The Campbell Hall Renovation project is nearing 25% completion as crews continue their facelift on the historic building.