The Ohio State Wexner Medical Center Inpatient Hospital – Central Sterile Supply project opened in February 2021. The project team constructed a central sterile supply building at Kenny and Ackerman roads to serve the Ohio State Wexner Medical Center hospitals and outpatient care centers. Total project budget was $45.3 million, paid with auxiliary (health center) funds.
Learn more about how Ohio State in investing in the spaces and places that empower collaboration by visiting Ohio State Environments.
Project Timeline
- 2018
- BoT professional services (Through DD)February 2018DesignJune 2018 - March 20192019
- BoT professional services (Remainder)February 2019BOT Construction ApprovalFebruary 2019ConstructionJuly 2019 - December 20202021
- Facility OpeningFebruary 2021
Project Team
Project Manager
George RiceProject Accountant
Brittney ColemanConsultants
AE/Design Architect: Henningson, Durham & Richardson (HDR)Construction Manager
Walsh/Turner (joint venture)News
-
In the News: Active Construction Changes Traffic Patterns on Game Days
Fans are back in Ohio Stadium this fall as the Buckeyes make another run toward the College Football Playoffs.
-
New Traffic Patterns
We all love scarlet and gray, but there’s a sea of orange on campus as Ohio State invests in the future of teaching, learning and research. Major construction projects are changing the way most Buckeyes will navigate campus – so allow extra travel time, be cautious near co
-
In the News: Facility opens to sanitize surgical equipment
The Columbus Dispatch recently reported on the opening of The Ohio State University Wexner Medical Center Central Sterile Supply facility. As reported, the first freestanding facility in Ohio dedicated to cleaning surgical equipment opened in February 2021.