Slideshow: Dodd Parking Garage

Mechanical and electrical plumbing system installation continues at Dodd Parking Garage, which is now 70% complete. Teams have poured concrete on six of seven levels of the facility, located on the corner of Medical Center and Old Cannon drives. The project will create parking spots for 1,100 vehicles. 

Additional construction activities include:

  • Pouring concrete on the elevator machine roof.
  • Masonry work in stairwell lobbies.
  • Installation reinforcement through level six.
  • Completion of concrete slab placement on level five.

The Dodd Parking Garage, located within walking distance of the Wexner Medical Center, is expected to open in June. View the photo slideshow above to track the project’s progress or view live construction feeds.