Slideshow: Biomedical and Materials Engineering Complex Phase 2

  • A future classroom where crews are preparing to pour concrete.
    A classroom space on the ground floor where crews are preparing to pour concrete.
  • A view of the main entrance which currently has dirt floor and pastic across the door.
    A view of what will be the main entrance where crews are working on above ceiling and wall rough-ins.
  • Crews digging a large hole.
    Crews digging out space to install footers.
  • A view of the electrical room with two large electric boxes in the wall.
    A view of the electrical room.
  • A view of the pump room.
    The pump room in the sub-basement features a permanent crane which can be useful if a piece of equipment needs to be lifted out for maintenance or replacement.
  • A view of the north connector where one side is clear construction plastic and the other side is a brick wall.
    Crews are working to fireproof the north connector.
  • A view of the air handler on the roof.
    A view of the air handler on the roof.
  • An exterior view of the building.
    An exterior view from the sixth floor.
  • An exterior view of the building.
    An exterior view of the building from the ground.

    Work on the Biomedical and Materials Engineering Complex (BMEC) Phase 2 is passing the halfway point, at nearly 53% complete. Crews are preparing to pour the second interior stairwell and then will be able to remove the exterior temporary set. Crews are also working on installing mechanical, electrical and plumbing (MEP) hangers throughout the building.

    Construction progress includes:

    • Pouring concrete in several locations in the coming days.
    • Installing MEP hangers, above ceiling and wall rough-ins.
    • Digging to install footers.
    • Air handler installed on roof.

    BMEC Phase 2 is a $94.3 million project that included the demolition of Watts Hall and renovates existing MacQuigg Hall while adding an addition which will house research and teaching labs, collaboration spaces, offices and classroom spaces. BMEC Phase 1, later renamed Mars G. Fontana Laboratories, opened in August 2020.

    View the live construction camera online.