    A vision is coming to life as construction crews continue their work on the University Square South building. With a March of 2023 opening date, crews have been working from the top down to complete the five-story mixed-use building. The project is about 70% complete with a budget of $44.9 million.

    The University Square project, led by Campus Partners, opens the front door of Ohio State and connects to the heart of the University District at 15th+HIGH.  Four main buildings and a new parking garage will anchor the project site.

    Construction progress includes:

    • Installing floor coverings, lighting and paint to the fourth and fifth floors.
    • Putting up drywall and paint on the third floor.
    • Installing plumbing and electric to the first and second floors.
    • Overhead inspections on first and second floors.