Crews worked to install solar panels on the canopy above the roof of the Energy Advancement and Innovation Center located at Carmenton, the university’s innovation district.
Four panels at a time were ganged together with two C-channels at ground level, then lifted by the crane to attach them to the structure. The steel attachments are predrilled to a 7-degree slope. The panels are installed slightly skewed to the building access so that they point due south. Each one will produce an output of approximately 400-watts of electricity.