Main navigation

Slideshow: Cannon Drive Stormwater Detention System

  • A view of the stormtraps from above the hole.
    A wide view of the construction site.
  • The stormtrap system with Ohio Stadium in the back.
    The Storm Trap system that will temporarily store runoff stormwater underground.
  • A view of crews digging out the site and preparing the sub-grade.
    Crews working to dig out the site and prepare the sub-grade for StormTrap installation.
  • Crews installing the StormTraps.
    Crews using an excavator to install Storm Traps.
  • A view from inside the site.  Geogrid is seen on the ground.
    Crews laying geogrid to strengthen and stabilize the dirt before installing Storm Traps.
  • Crews working to prepare the dirt.
    Crews working to prepare the sub-grade.

    A stormwater detention system with the ability to hold up to seven acre-feet (more than two million gallons) of storm water is being installed at the Cannon Drive Relocation – Phase 2 site. 

    Crews start by digging out the site and preparing the sub-grade. Next, geogrid is placed in the base stone, followed by installation of Storm Traps. Once complete, the system will temporarily store runoff underground before releasing it at a controlled rate to avoid flooding and other effects of stormwater runoff. 

    As Storm Traps continue to be loaded onto the site, Tom Ekegren, Facilities Design and Construction (FDC) project manager of Cannon Drive Relocation- Phase 2 said crews are installing sections of the system to reduce the amount of time the subbase is exposed to weather. 

    “Hundreds of trucks are bringing in different equipment daily,” said Ekegren. “We have safety plans in place and we also ask drivers and pedestrians to follow the instructions of signage and be aware when nearing construction zones.” 

    The system will help with the 500-year flood protection for the Columbus campus and meets the intent of the city of Columbus’ design manual. 

    View live updates and learn more about the project.