Main navigation

Slideshow: Inpatient Hospital

  • A view of the lobby where Terrazzo floors are seen finished with a large Block O on wood near the ceiling.
    The ground level lobby where crews are preparing to move furniture in.
  • A view of the outside area where crews are seen installing asphalt.
    Crews have started to install asphalt outside of the main entrance.
  • A small coffee bar is seen next to a wall of windows.
    A view of the coffee bar which is located under the escalators on the ground level.
  • A view of two escalators with large white tarps covering them and a set of stairs between.
    A view from the ground level looking up the stairs and escalators to the second level.
  • A view of a large loading dock outside with lights at the top of several structural pillars.
    A loading dock area which Fit-up crews are currently using to bring furniture in.
  • A view of of the exterior of a brick building with a large black tarp covering working space.
    The exterior of the building which shows where crews are installing a surgery connector, which will allow medical staff to use a sterile hallway during procedures.
  • A view of a hospital room with no furniture in it. A Block O can be seen engraved in the wall.
    An intensive care unit (ICU) room on the 10th level.
  • A large room is seen with large windows along the left side of the area.
    A view of the 24th level looking into the nursery where crews are finishing up framing and preparing to begin drywall installation.
  • Three elevators are seen completed, well lit and clean with their doors open.
    The public elevators are complete and ready for use.

    Work on The Ohio State University Wexner Medical Center inpatient tower is nearing 90% complete as crews have turned over the first floor to fit-up, and are now installing furniture, medical equipment, technology, signage and art. 

    “We’re very close to milestone two, which includes levels two, four, seven, eight and 10 being ready for fit-up,” said Kristin Poldemann, associate vice president of Facilities Design and Construction, in the latest episode of the City of Ohio State Podcast. “So that will bring the other major public floors to completion.”

    The upper levels are wrapping up framing and beginning drywall installation. A quaint coffee bar has been installed under the escalator on the ground floor lobby to welcome guests as they enter. The public elevators are complete and ready to be used.

    “We’re making excellent progress,” said Ragan Fallang, project manager of the inpatient tower. “We are excited to start bringing the hospital’s design to life with medical equipment, technology and other finishing touches that will serve both patients and healthcare professionals.” 

    Construction progress includes:

    • Final paint and plumbing touches on level 10
    • Preparing levels four, seven, eight and 10 for turnover
    • Exterior asphalt installation has begun on the West 10th Ave side of the building
    • Finishing up framing and preparing for drywall installation on 24th level
    • Public elevators are installed and ready for use

    On track to open in early 2026, the 1.9 million-square-foot inpatient hospital is the largest single facilities project ever undertaken at Ohio State with up to 820 beds in private-room settings to elevate patient-centered care, safety and training for the next generation of health care providers. 

    View construction progress on the live cameras.