Construction on The Ohio State University Wexner Medical Center Outpatient Care Powell is about 42% done with just about every tradesperson conducting work on the building. From masonry and roofing, to framing and mechanical electric and plumbing (MEP), significant progress is being made. Precast on the exterior of the building is now complete as brick and windows are being installed.
Construction progress includes:
- Curtain wall on the southwest corner being installed.
- Overhead MEP being installed on the ground floor.
- In-wall framing being installed on the ground floor.
- Sheetrock installation beginning on floors two and three.
- Plumbing beginning on floors three and four.
Outpatient Care Powell is being built on almost 30 acres of land at the northeast corner of home Road and Sawmill Parkway, across from Olentangy Liberty High School. The $183 million project includes 200,000 square feet and will design and build a five-story medical office building and a two-story ambulatory health center which includes imaging, outpatient rehab/PT, endoscopy and support services.
View the live construction camera online.