Ohio State is in the process of revising websites and program materials to accurately reflect compliance with the law. While this work occurs, language referencing protected class status or other activities prohibited by Ohio Senate Bill 1 may still appear in some places. However, all programs and activities are being administered in compliance with federal and state law.

Main navigation

Slideshow: Interdisciplinary Health Sciences Center

    Phase 3 of construction on the Interdisciplinary Health Sciences Center is nearing 60% complete. This third and final phase includes a 120,000-square-foot renovation of Hamilton Hall, which is poised for completion in March 2024. The Classroom Wing, Phase 2, is on track for a move-in date of mid-July. The Anatomy Wing, Phase 1, opened in January 2022.

    Construction progress includes:

    • Nearing completion of fully enclosing the forum.
    • Preparing to pour slab of wellness & fitness rooms on the lower level.
    • Finishing framing and overhead rough-ins on the second floor.
    • Welding metal deck at slab infill.
    • Installing the skylight on the forum.

    The Interdisciplinary Health Sciences Center will provide upgraded and flexible facilities to create a collaborative campus for interprofessional education throughout the Health Sciences.