Main navigation

Slideshow: Campbell Hall

  • A view of the ground floor of the building where the ground is made of dirt. There are cement walls and it's being used as a storage area.
    Underground plumbing being installed on ground floor.
  • A view of a hallway split in two different directions.
    Crews are working to install floor fill on the second floor after removing old concrete.
  • A long hallway with wood doors seen along it on each side and the middle of the ceiling the whole way down is taken out.
    A view of a hallway on the third floor where crews are installing mechanical, electrical and plumbing (MEP) in the ceiling.
  • A view of two levels of floors dimly lit with construction happening all around.
    A view from the third floor looking down to the ground floor which will be used as a community space.
  • An exterior view of the building where windows are seen boarded up and a large tree is on the right side of the photo with bright orange leaves.
    A view of the exterior window work being done.
  • An exterior view of the building where two large concrete pillars are in the middle behind a large set of stairs leading up to the building.
    A view of Campbell Hall from Neil Ave.

    The renovation of Campbell Hall is nearing the 10% complete mark as crews continue interior work. They’ve completed removing old concrete floors from the building and are now refilling them and bringing them back up to the proper elevation. Underground plumbing is being installed on the ground floor as the penthouse roof is being removed. Historic preservation is being considered as crews work through the project, preserving wood doors and frames throughout the building and the terracotta entrance to the auditorium. 

    Construction progress includes:

    • Installing floor fill on the second floor. 
    • Mechanical, electrical and plumbing (MEP) being installed on the third floor.
    • Underground plumbing being installed in the basement. 
    • Crews preparing to do exterior window restoration.

    The original building, completed in 1916, was built to house the home economics department. Now, Campbell Hall houses some of the programs of the College of Education and Human Ecology’s Department of Human Sciences and Educational Studies.

    The Campbell Hall Renovation is a $61.2 million project that includes state funding and supports the College of Education and Human Ecology’s educational goals and mission. It renovates 115,000 square-feet of existing offices, research and computer labs, teaching kitchen, department and pool classrooms and collaborative areas.