News: Biomedical and Materials Engineering Complex (Advanced Materials Corridor)

  • Slideshow: Biomedical and Materials Engineering Complex Phase 2

    Work on the Biomedical and Materials Engineering Complex (BMEC) Phase 2 is passing the halfway point, at nearly 53% complete. Crews are preparing to pour the second interior stairwell and then will be able to remove the exterior temporary set. Crews are also working on installing mechanical, electrical and plumbing (MEP) hangers throughout the building.

    Construction progress includes:

  • Slideshow: Biomedical and Materials Engineering Complex Phase 2

    Construction on the Biomedical and Materials Engineering Complex (BMEC) Phase 2 is about 45% complete as crews recently finished installing the final concrete piers. The focus is now on ensuring a strong foundation with footers and a foundation wall. Construction on the north and south connectors from Mars G.

  • Slideshow: Biomedical and Materials Engineering Complex Phase 2

    Work on the Biomedical and Materials Engineering Complex Phase 2 (BMEC) is nearly halfway complete as crews have made substantial progress over the last several months. A buck hoist has been installed and a platform below it is in place to ensure the safety of everyone on site. 

  • City of Ohio State Podcast Season 3 Episode 1: Campus Construction

    As another outpatient care center gets approved for construction and new academic and research projects break ground, we kick off season 3 of the City of Ohio State Podcast with Kristin Poldemann, the associate vice president of Facilities Design and Construction to talk about current projects across campus. 

  • Slideshow: Biomedical and Materials Engineering Complex - Phase 2

    Construction on the Biomedical and Materials Engineering Complex – Phase 2 is ramping up after beginning in October 2023. Crews are finished with interior abatement and are now focusing on structure and exterior façade demolition. 