NEWS: CANNON DRIVE RELOCATION – PHASE 2

Slideshow: Cannon Drive Relocation Phase 2

Construction on the Cannon Drive Relocation Phase 2 project is almost at the halfway point. At about 40% completion, between 30 and 50 workers make their way to the site daily aiming for a December 2024 completion date.

Cannon Drive, CABS Updates

Cannon Drive Relocation – Phase 2 progress continues. The intersection of John Herrick Drive and Cannon Drive, originally anticipated to reopen in August 2023, will reopen in late September 2023.

Slideshow: Cannon Drive Relocation – Phase 2

Cannon Drive Relocation – Phase 2 rebuilds the roadway between John Herrick Drive and Woody Hayes Drive at its current elevation and constructs a certified ODNR flood protection levee. When finished, the project will add up to 500-year flood protection for the Columbus campus.