Ohio State is in the process of revising websites and program materials to accurately reflect compliance with the law. While this work occurs, language referencing protected class status or other activities prohibited by Ohio Senate Bill 1 may still appear in some places. However, all programs and activities are being administered in compliance with federal and state law.

Main navigation

News

  • Slideshow: Biomedical and Materials Engineering Complex Phase 2

    Work on the Biomedical and Materials Engineering Complex (BMEC) Phase 2 is passing the halfway point, at nearly 53% complete. Crews are preparing to pour the second interior stairwell and then will be able to remove the exterior temporary set. Crews are also working on installing mechanical, electrical and plumbing (MEP) hangers throughout the building.Construction progress includes:Pouring concr...
  • Slideshow: Waterman – Multispecies Animal Learning Center (MALC)

    The CFAES Waterman Agricultural and Natural Resources Laboratory’s Multispecies Animal Learning Center (MALC) facility is coming to life as crews have begun installation of electrical conduits in the mezzanine area as well as plumbing for restrooms. Next, they’re preparing to pour concrete slabs for the floor base, followed by interior partitions and mechanical, electrical, and plumbing rough-in....
  • Slideshow: Outpatient Care Powell

    Work on The Ohio State University Wexner Medical Center Outpatient Care Powell is nearing 33% completion. Crews are just beginning framing and overhead ceiling work on the fourth floor, while already complete on floors two and three. Installation of the roof on the Ambulatory Healthcare Center (AHC) is 80% complete. Final grading and seeding are slated for the coming months as crews also begin tr...
  • Slideshow: Inpatient Hospital

    Work on The Ohio State University Wexner Medical Center Inpatient Hospital has reached 92% complete. Floors one through four and seven through 10 have been turned over to the fit-up team to install furniture, medical equipment, technology, signage and art. More than 80,000 new items, not including IT and furniture, are set to be installed over the coming months. Patient rooms are starting to...
  • Waterman - Multispecies Animal Learning Center Begins to Take Shape

    The Waterman – Multispecies Animal Learning Center (MALC) facility is beginning to take shape as crews have finished pouring the concrete foundations for the main arena and the structural steel has begun to arrive to start going vertical.“Since beginning mass excavation and grading in July, more than 50,000 cubic yards of dirt have been moved on site,” said Chris Kuhn, project manager of the MALC...