NEWS: OLD CANNON GARAGE

Old Cannon Garage Updates

Old Cannon Garage will no longer open on Monday, August 1. A new opening date is still to be determined. The university is working quickly to address the issue and will provide timing updates as additional information becomes available.

Slideshow: Old Cannon Garage

Construction on the Old Cannon Garage, previously known as the Dodd Parking Garage, is nearly complete. Crews are installing elevators, exterior glass, signage, pavement markings and making final preparations for faculty and staff.

Slideshow: Dodd Parking Garage

Mechanical and electrical plumbing system installation continues at Dodd Parking Garage, which is now 70% complete. Teams have poured concrete on six of seven levels of the facility, located on the corner of Medical Center and Old Cannon drives. The project will create parking spots for 1,100 vehicles. 

Additional construction activities include:

In the News: Active Construction Changes Traffic Patterns on Game Days

Fans are back in Ohio Stadium this fall as the Buckeyes make another run toward the College Football Playoffs.

For a winning fan experience, The Ohio State University is encouraging attendees to allow additional time to get in and out of the stadium area as traffic and parking changes may cause delays.

Photo Slideshow: Dodd Parking Garage

Concrete pours and rebar installation continue on the Dodd Parking Garage, which is more than 30% complete. Overnight concrete pours are ongoing and will continue through January 2022. The garage will have six levels and 1,100 parking spaces for Ohio State faculty and staff.

Additional construction activities include: